Exclusive development Oracle Apartments

Exclusive development Oracle Apartments
The construction progress, July 2011

  • The installation of incoming gas, water and BT services inclusive of meters has been completed.
  • The felt roofing inclusive of the mansafe system is complete and the installation of all roof lightning is complete
  • The installation of windows and glass balustrades on all levels is well advanced
  • The internal lift installation is substantially complete
  • The installation of external cladding is well progressed and should be complete in a couple of weeks
  • The installation of internal portioning has commenced in flats 4 and 6
  • The installation of the internal cast iron rain water drainage has commenced
  • The dry riser, landlord area, mechanical ventilation, kitchens, sanitary ware and tiling packages are all currently being are all currently being procured